Crew: 5 | CDR - David M. Walker |
Plt - Ronald J. Grabe | |
MS 1 - Mark C. Lee (EV 2) | |
MS 2 - Norman E. Thagard (EV 1) | |
MS 3 - Mary L. Cleave | |
Launch | 4 May 1989 @ 1446:59.0682 EDT |
Orbital incl: | 28.89 |
Max alt: | 331.5 km. |
Orbits: | 64 |
Dur: | 4:00:57:27 |
Landing: | 8 May 1989 @ 1243:26 PDT |
Launch Window: | 1 hour, 4 minutes (1:48 - 2:52 pm EST) |
Planetary window for Magellan: | 31 days, 28 April - 28 May 1989 |
TAL Sites: | Ben Guerir (alternate Moron), contingency in-plane abort: Banjul, alternate: Bermuda |
AOA site: | Edwards AFB (alternate WS and KSC) |
Primary landing site: | Edwards AFB |
Landing Speed: | 196 knots (225 mph) |
Landing rollout: | 10,295' from main gear touchdown |
Vehicle weight @ liftoff: | 4,536,344 lbs |
Orbiter weight @ liftoff: | 261,118 lbs |
Orbiter weight @ landing: | 192,459 lbs |
Cargo mass approx.: | 47,909 lbs |
Landing Weight: | 7,701 lbs |
Special mission kits: | EMU's 1096, 1095, Galley, TAGS, Teleprinter, no RMS |
Magellan Venus Probe/IUS-#18 - 1989-033B | Deployed mass - 45,799 lbs. Probe mass - 7,383 lbs |
Mid-deck | FEA-2 (Floating Zone Crystal Growth and Purification), MLE (see STS-26), AMOS (see STS-29). |
SSME's: | 2027 (1), 2030 (2), & 2029 (3) - All 2nd use. At Tower Clear 104% |
OMS Pods/Engines: | LP-99/106 - Pod 9th use, Motor 10th use & RP-99/111 - Pod 9th use, Motor 5th use |
ET: | ET-29 (LWT-22) |
SRB's: | BI-027 (RSRM-4) - Set successfully recovered, No. 2 LH SRB chute collapsed after infation |
Left - 27A | Right - 27B | |||
New | ? | Fwd | ? | ? |
? | ? | Cyl | ? | 21 |
ETM1 | ? | Cyl | ? | New |
? | ? | Cyl | ? | ? |
New | ? | Cyl | ? | New |
New | ? | Cyl | ? | ? |
? | ? | Cyl | ? | Q6 |
? | ? | Att | ? | D9 |
ETM1 | ? | Stf | ? | ? |
ETM1 | ? | Stf | ? | ? |
? | ? | Aft | ? | ? |
12 December 1985 | ET-29 arrives on dock KSC |
14 December 1988 | OV-104 returns to the OPF following Mission-27 |
2 March 1989 | ET/SRB mate |
11 March 1989 | OV-104 rollover from OPF-2 to VAB High Bay 3 for stacking the following day |
22 March 1989 | Stack rollout to Pad 39B |
25 March 1989 | Magellan payload loaded aboard Atlantis at Pad 39B |
7 Apri l 1989 | TCDT dress rehearsal conducted with crew aboard orbiter |
1 May 1989 | Astronaut arrival KSC. Also the hydrogen recirculation pump/line were replaced on Atlantis |
2 May 1989 | "Call to stations" 43 hr countdown started at 8 am EDT |
4 May 1989 | Launch |
8 May 1989 | Landing at Edwards AFB |
13 May 1989 | First leg of ferry flight from Edwards AFB to Briggs Army Air Base, El Paso for an overnight stay |
15 May 1989 | Final leg from Biggs AAB to Dallas/Ft. Worth Int. Airport to Warner Robins AFB to KSC OPF-2 (one day hop) |
10 August 1990 | Venus Orbit insertion for Magellan |
?? October 1994? | Magellan re-enters Venus' atmosphere |