Mission 37
STS-38
1990-097A
Crew: 5 CDR - Richard O. Covey
Plt - Frank L. Culbertson
MS 1 - Carl J. Meade (EV 2)
MS 2 - Robert C. Springer (EV 1)
MS 3 - Charles D. Gemar
Launch 15 November 1990 @ 1848:15 EST
Orbital incl: 28.47
Max alt: 270.4 km.
Orbits: 80
Dur: 4:21:54:28
Landing: 20 November 1990 @ 1642:43 EST
Launch Info: Orbiter - Atlantis 104-7 Pad 39A KSC (MLP-1) - Hold time of
2 minutes, 15 seconds for unspecified reasons. Last "Classified" DOD flight and 5th night
launch. Landed at KSC/SLF runway 33, 6th KSC landing. Delayed one day from
19 November due to high winds at Edwards, diverted to KSC on 20 November when
situation did not imporove at EAFB (had been scheduled for 1:48 pm PST)

MISSION PARTICULARS
Launch Window: DOD announced period: 6:30 - 10:30 pm EST (Actual window: 1 hour, 26 minutes; 6:46 - 8:12 pm EST)
TAL Sites: Banjul (backup: Ben Guerir)
AOA site: Edwards AFB
Primary landing site: Edwards AFB, scheduled at 19 November, 3:41 pm PST
Landing Speed: 194 knots (223 mph)
Landing rollout: 8,900' from main gear touchdown
Vehicle weight @ liftoff: 4,531,909 lbs
Orbiter weight @ liftoff: 191,091 lbs (without cargo)
Orbiter weight @ landing: N/A
PAYLOADS
Cargo mass approx.: N/A
Landing Weight: N/A
Special mission kits: EMU's 2010 & 2011, Galley, teleprinter, no RMS
PRIMARY PAYLOADS
DOD-05 AFP-658/IUS (Classified) - 1990-097B/USA-67 In geosynchronous orbit according to RAE, and was reportedly deployed on FD-2
SECONDARY PAYLOADS
Mid-deck AMOS (see STS-29R), APE-B (see STS-9), VFT-1 (see STS-44), and SpaDVOS (see STS-27R)
SHUTTLE STACK COMPONENTS
SSME's: 2019 (1) - 7th use, 2022 (2) & 2027 (3) - Both 5th use. At Tower Clear 104%
OMS Pods/Engines: LP-01/106 - Pod 4th use, Motor 13th use, & RP-03/114 - Pod 12th use, Motor 5th use
ET: ET-40 (LWT-33) - Replaced ET-27 due to leaking 17 in. disconnect
SRB's: BI-039 (RSRM-12) - Set successfully recovered
SHUTTLE STACK COMPONENTS
Left - 39A Right - 39B
28 047 Fwd 045 29
28 079 Cyl 081 29
28 011n Cyl 014n 29
27 L82 Cyl L88 22
29 L36n Cyl L35n 29
27 L101 Cyl L117 New
New L27n Cyl L32n 28
New L41 Att L08 28
New L65 Stf L66 New
30 013 Stf 026 TEM4
New 050 Aft 048 28
7th DOD Mission
MISSION MILESTONES:
20 February 1990 ET-37 arrives on dock KSC
9 March 1990 ET-40 arrives on dock KSC
14 March 1990 OV-104 returns to the OPF following Mission-34/STS-36
14 May 1990 ET-37/SRB mate
8 June 1990 OV-104 rollover from OPF-2 to VAB High Bay 1 for stacking the next day
18 June 1990 Stack rollout to Pad 39A
21 June 1990 TCDT countdown dress rehearsal counducted with crew aboard
29 June 1990 Hydrogen leak test reveals 2 leaks during mini tanking test
25 July 1990 2nd leak test with quick fixes in place reveals persistent leak
9 August 1990 Stack rollback to VAB High Bay 1
10 August 1990 Stack rolled into VAB after waiting outside for STS-35 to rollout to Pad 39A (tiles damaged by hail)
14 August 1990 Stack disassembled to add new ET-40 tank
15 August 1990 OV-104 returned to OPF
12 September 1990 ET-40/SRB mate
2 October 1990 OV-104 rollover to VAB High Bay 1 for restacking next day (minor repairs were made in the OPF first)
3 October 1990 OV-104 remated to the new ET/Stack
12 October 1990 Stack returned to Pad 39A
24 October 1990 Hydrogen leak test at pad to clear Atlantis for flight (partial LH2 loading - mini tanking)
11 November 1990 "Call to stations" 43 hr countdown started at 11:30 pm EST, started early to accommodate Titan-IV
12 November 1990 Astronaut arrival KSC
15 November 1990 Launch
20 November 1990 Landing at KSC/SLF & OV-104 returned to OPF-2